LatestConstruction Progress UpdateOur works at the construction site continue in accordance with the planned schedule. Across the site, reinforced concrete, wall, pool and finishing works continue to progress in line with the planned schedule.Read the reportHide
Our works at the construction site continue in accordance with the planned schedule. Across the site, reinforced concrete, wall, pool and finishing works continue to progress in line with the planned schedule.
D Block
- Reinforced concrete works for the basement shear walls have been completed.
- Column and shear-wall reinforcement installation and formwork works are ongoing.
A and B Pools
- Reinforced concrete works for the balancing tanks of pools A and B have been completed.
- After the insulation works, backfilling and the lean-concrete layer under the raft foundations will follow.
C Block
- The raft foundation concrete of the second basement level has been completed.
- Single-sided shear-wall formwork is ongoing; shear-wall reinforcement installation will follow.
B1 and B2 Blocks
- Brick wall works on the ground and first floors have been completed.
- Wall works on the upper floor and at roof level are ongoing.
- The first plaster coat (scratch coat) has started on the ground floor of B1 Block.
D, E and F Pools
- The raft foundation reinforcement of Pool D has been completed, and shear-wall reinforcement installation is ongoing.
- Raft foundation formwork for Pool E is planned to start.
- Raft foundation formwork and membrane insulation for Pool F have been completed; reinforcement installation is next.